一個項(xiàng)目的項(xiàng)目經(jīng)理被替換,新的項(xiàng)目經(jīng)理識別到項(xiàng)目超出預(yù)算并落后于進(jìn)度計劃。新項(xiàng)目經(jīng)理首先應(yīng)該做什么?()
A、要求項(xiàng)目發(fā)起人增加預(yù)算并延長進(jìn)度計劃
B、獲得項(xiàng)目發(fā)起人的批準(zhǔn),重新組織團(tuán)隊
C、減少項(xiàng)目范圍以滿足原始預(yù)算和進(jìn)度計劃
D、識別改進(jìn)領(lǐng)域和加強(qiáng)監(jiān)督